Connect with ASBI
9901 Brodie Lane, Suite 160 PMB 516 • Austin, TX 78748
Phone: 512.523.8214
Copyright © 2023 American Segmental Bridge Institute
The $426 million I-4/Selmon Expressway Connector provides a connection between Interstate 4 (I-4) and the Selmon Expressway in Tampa, Florida. This facility, which includes dedicated truck lanes, services approximately 10,000 trucks a day, reducing traffic on local city streets and improving safety. The Connector also provides additional route options for the traveling public, including convenient access to the Selmon Expressway from I-4, the Tampa cruise terminal, local beaches, Tampa International Airport, and flexibility for hurricane evacuation.
Innovation of Design and/or Construction
Innovations used in the design were:
Numerous innovative methods were used during construction to maximize efficiencies in safety, quality, and production, including:
Rapid Construction
Due to unexpected available funding, the consultants were asked to shorten Florida Department of Transportation’s (FDOT) original design schedule. The consultants added design resources, allowing the completion of all design work three months ahead of FDOT’s new schedule.
The original anticipated construction schedule was 1,065 days, which was 753 days ahead of the maximum 1,818 days in FDOT’s Request for Proposals. The project team accomplished this by using eight casting machines to accelerate the fabrication of the bridge components. As many as six drilled shaft crews and multiple substructure crews were implemented to expedite the construction of the foundation and substructure elements. For segment erection, five balanced cantilever erection crews working day and night shifts and one span-by-span erection crew were used to reduce the overall project schedule. These crews, combined with state-of-the-art erection equipment, including mobile segment lifters for top-down erection, greatly exceeded production cycles originally anticipated. In addition, top-down erection equipment was used to minimize the number of lane closures and detours, which resulted in reduced impacts to the traveling public.
Aesthetics and/or Harmony with the Environment
Nearly all of the required 75 right-of-way parcels involved remediation for contamination. Contamination cleanup, including remediation of dewatering operations, transpired concurrently with construction. The cleanup effort greatly enhanced the quality of the environment in and around Ybor City.
The project also included addressing impacts to McKay Bay Park, a valued Section 4(f) resource and environmentally-sensitive habitat for migratory shorebirds. A two-year coordination process with the City of Tampa and the Federal Highway Administration was required to obtain approval. The result was a reduction in pollutants discharging into the preserve. Stormwater management facilities were established to enhance untreated waters prior to entering McKay Bay and areas of Tampa Bay surrounding Port Tampa Bay.
The project team worked diligently with community agencies and business leaders to develop context sensitive and harmonizing architectural aesthetics which incorporated the brick and color patterns well established within the fabric of the Ybor City community, Palmetto Beach Historic Districts and Tampa’s McKay Bay Park. This includes the historically-themed exterior treatment the 7th and 4th Avenues Gateway underpass facades, the toll plaza gantry and supporting structural members, and the retaining wall panel facades throughout the project.
Cost Competitiveness
The estimated construction cost was originally $446 million. Through the alternative bid package process, the project was completed at a construction cost of $429 million, resulting in a net savings of $17 million.
Minimization of Construction Impact on the Traveling Public
The design teams preserved one bridge in the median of I-4 that was slated for demolition during a prior construction project. This bridge was used as construction access and also as a median diversion during construction of the bridges overhead, resulting in a reduced construction impact to the traveling public.
During construction, top-down span-by-span and balanced cantilever segment erection equipment and methods were implemented to minimize impact to the traveling public, the railroad, and to environmentally-sensitive areas of the project.
Overall, the community was extremely supportive of the project. FDOT received minimal complaints from the traveling public, nearby residents, or other parties during project construction.
Jury Comments
The project demonstrated how segmental construction can provide obstruction free, fast and flexible bridge erection in a highly congested urban/environment. The Florida DOT should be commended for allowing the designers and contracting team to take every advantage that segmental construction affords to orchestrate the building of this very complex urban interchange within budget and schedule.
2015 ASBI Award of Excellence
Category: Urban Bridges
State:
Florida
Owner:
Florida Department of Transportation
Designer:
Atkins, FIGG Bridge Engineers, Inc., and Parsons Brinckerhoff, Inc.
Contractor:
PCL / Archer Western, a Joint Venture (PCLAW)
Construction Engineering Services:
Corven Engineering, Inc., and McNary Bergeron & Associates
Construction Engineering Inspection:
Cardno TBE, Johnson-Adams & Associates, LLC, and FIGG Bridge Inspection, Inc.
Precast Producer:
PCL / Archer Western, a Joint Venture (PCLAW)
Formwork for Precast Segments:
EFCO Corp.
Erection Equipment:
Deal and Beijing Wowjoint Machinery Co.
Post-Tensioning:
VStructural, LLC (VSL)
Bearings:
COSMEC. Inc.
Expansion Joints:
Watson Bowman Acme
Epoxy Supplier:
Pilgrim Permocoat, Inc
Prepackaged Grout:
Euclid Chemical, Inc.